Enrollment continues to increase in Crosby ISD, with many elementary campuses accommodating more students than the designed capacity of the campus. In addition, many district facilities are aging and require updates to building systems, safety features, and learning spaces. A bond would allow the district to address growth and long-term facility projects that are not funded through the regular operating budget.
-
State law separates school funding into two parts. Maintenance & Operations (M&O) funds pay for day-to-day costs, such as salaries and utilities. Large facility projects, like new construction, are funded through bonds, which require voter approval. Bond debt is repaid using a separate tax rate called Interest & Sinking (I&S). This is why the district uses a bond, rather than the regular operating budget, to pay for large facility projects.
-
Yes. Over the past decade, Crosby ISD’s total tax rate has decreased, even as property values have grown.
-
If the bond does not pass, the district would continue to operate current facilities and address only the most urgent items as funding allows. Major renovations and new facilities would be delayed.
-
If approved, project planning would begin after the election. Construction would occur in phases over multiple years.
-
Projects were recommended by a community committee, the Long-Range Planning Team, and reviewed by the Board of Trustees before being placed on the ballot.
-
Bond funds must stay within the purposes voters approved. If costs or circumstances change, the district can adjust project scope or timelines, but any changes require Board action and must remain within the purposes approved in the election. Bond funds cannot be redirected to purposes outside what voters approved, such as salaries, utilities, or daily operations.
-
Texas school districts are required by state law to follow specific rules when hiring construction companies for bond-funded projects. These rules help ensure fair competition, financial accountability, and quality work on public facilities.
Companies must generally meet these requirements to be eligible:
Be properly registered to do business in Texas
Hold required state licenses for specialized trades (such as electrical, plumbing, or HVAC work)
Carry required insurance, including general liability and workers' compensation coverage
Provide payment and performance bonds, as required by state law for public contracts
Show relevant experience with similar construction projects, including prior work for public school districts when applicable
Provide financial references demonstrating the ability to complete the project
Disclose any conflicts of interest with district officials, as required under Texas law
Bond Propositions
-
The combined bond package totals $208,280,000, divided into two separate propositions: Proposition A ($98,280,000) and Proposition B ($110,000,000).
-
State law allows districts to divide bond packages into separate propositions so voters can decide on each independently. Voters may approve one, both, or neither proposition.
-
Yes. Each proposition is voted on separately. If only one is approved, only that proposition's projects and tax impact would move forward.
-
Proposition A is a $98,280,000 proposition that would fund a new elementary school and five districtwide facility projects.
-
Proposition B is a $110,000,000 proposition that would fund construction of a new middle school to replace Crosby Middle School, built in 1974.
-
Based on an average taxable home value of $115,728 (after the standard homestead exemption), the estimated combined impact — if both propositions are approved — is approximately $1.93 per month, or $23.15 per year.
-
Homeowners age 65 or older, or those with a qualifying disability, who have applied for the applicable exemption generally will not see their school tax bill increase as a result of the bond, unless the home is significantly improved or another legal exception applies.
-
Proposition A includes a new elementary school and five districtwide projects: HVAC updates and improvements, roof replacement and improvements, site improvements, safety and security improvements, and technology infrastructure upgrades.
-
Student enrollment continues to increase as the Crosby ISD community grows. Based on projections by professional demographers, all but one of the Crosby ISD elementary schools are projected to exceed campus capacity by 2029, with more than half exceeding 120% of capacity by 2030.
-
This districtwide project includes access control, security cameras, and traffic flow improvements across campuses.
-
This project funds network and device infrastructure supporting classroom instruction districtwide.
-
Crosby Middle School was built in 1974. Its foundation, roof, and mechanical/electrical/plumbing systems have been under engineering investigation since January 2024.